Flood-Damaged Bridge Cuts Off Multiple Villages in Valsad

By GS Team
4 Aug 20262 mins read
TukuTouch Logo
Valsad floods destroyed Lilapor bridge, isolating 10-15 villages. Delayed new bridge, 80% complete but stalled by Customs office relocation, sparks public anger. Residents risk crossing damaged bridge, demanding immediate alternative routes and inter-departmental coordination to expedite the new bridge and restore vital connectivity.

Summarized by AI; it may make mistakes. Check important info

Flood-Damaged Bridge Cuts Off Multiple Villages in Valsad

Heavy flooding in Valsad has severely damaged the old bridge at Lilapor village, forcing authorities to suspend vehicular movement and cutting off connectivity for nearly 10 to 15 villages. Residents have blamed delays in the completion of a new bridge, alleging a lack of coordination between the Public Works Department (PWD) and the Customs Department.

The old bridge developed a massive sinkhole after floodwaters washed away a portion of its structure, making it unsafe for all vehicles, including two-wheelers. With the bridge closed, residents are facing difficulties in travelling to Valsad city and nearby villages.

Residents Forced to Walk Across Damaged Bridge

The closure has disrupted the daily routine of students, office-goers and villagers, many of whom are now taking long detours to reach their destinations.

Some residents have even been crossing the damaged bridge on foot, risking their lives due to the absence of an alternative route.

New Bridge 80% Complete, Work Stalled

A new bridge is being constructed adjacent to the old one, and around 80% of the work has already been completed.

However, the remaining work has reportedly been delayed because a Customs Department office located on the bridge approach road is yet to be relocated. Residents said the lack of coordination between the PWD and the Customs Department has stalled the project despite it being close to completion.

Residents Seek Immediate Action

Locals have urged the authorities to expedite coordination between the two departments so that the remaining work on the new bridge can be completed and traffic restored at the earliest.

They have also demanded an immediate alternative route to ensure safe movement until the new bridge is opened for public use.