Rail Quadrupling Work at Dahanu Road To Disrupt Train Services On October 11; Six Trains Delayed

By GS Team
10 Oct 20262 mins read
TukuTouch Logo
Train services face disruptions on October 11 due to VNG EI commissioning for the Virar-Dahanu Road railway quadrupling project. Three trains will have changed originating/terminating stations (Borivali-Vatva, Virar-Surat, Surat-Virar), while six services will depart late by 30 minutes to 1 hour 45 minutes. Additional trains may also experience delays. Passengers are advised to check updated schedules and plan journeys accordingly.

Summarized by AI; it may make mistakes. Check important info

Rail Quadrupling Work at Dahanu Road To Disrupt Train Services On October 11; Six Trains Delayed
Image : AI Generated Representative image

Train services will be affected on October 11 due to VNG EI commissioning work being carried out as part of the railway quadrupling project between Virar and Dahanu Road. The work will lead to changes in the originating and terminating stations of three trains, while six other services will depart later than scheduled. Several additional trains may also face delays due to the impact on railway operations.

According to railway officials, passengers travelling on the affected routes have been advised to check train timings and plan their journeys accordingly.

Three Trains To Operate From Changed Stations

The originating and terminating stations of three trains have been changed in view of the commissioning work.

●     Train No. 19417, Borivali–Vatva: Will now originate from Vapi.

●     Train No. 19001, Virar–Surat: Will now originate from Valsad.

●     Train No. 19002, Surat–Virar: Will terminate at Dahanu Road.

Passengers boarding or alighting at the affected stations should check the revised arrangements before travelling.

Six Trains To Depart Late On October 11

Railway officials have announced delays ranging from 30 minutes to 1 hour 45 minutes for the following six trains:

Train Number and Route
Expected Delay
12925 Bandra Terminus–Amritsar
1 hour 30 minutes
12216 Bandra Terminus–Delhi Sarai Rohilla
1 hour 45 minutes
14708 Dadar–Hanumangarh
30 minutes
12480 Bandra Terminus–Jodhpur
1 hour
19217 Bandra Terminus–Veraval
30 minutes
12933 Bandra Terminus–Vadodara
30 minutes

More Trains May Face Delays

Apart from the six rescheduled services, several other trains may run 30 to 40 minutes behind schedule due to the technical work.

Some trains may also be detained for periods ranging from 30 minutes to two-and-a-half hours. Railway officials have indicated that around 10 to 15 mail and express trains could experience additional delays of 15 to 20 minutes due to the cascading impact on other services.

Passengers Advised To Check Train Timings

The commissioning work is part of the railway quadrupling project between Virar and Dahanu Road. Passengers travelling on October 11 are advised to verify their train schedules and check the revised originating and terminating stations before leaving for the railway station.