Ahmedabad’s ₹52.92-Crore Danapith Fire Station Ready, Set to Open Within 15 Days

By GS Team
20 Nov 20263 mins read
TukuTouch Logo
Ahmedabad's new Danapith Fire Station in Khadia is ready to open soon. The ₹52.92 crore project includes a modern fire station, 31 staff quarters, and multi-level parking for 525 vehicles. Despite heritage and traffic delays, the facility, equipped with advanced amenities, awaits final approvals to become operational within 15 days, enhancing city safety.

Summarized by AI; it may make mistakes. Check important info

Ahmedabad’s ₹52.92-Crore Danapith Fire Station Ready, Set to Open Within 15 Days

Ahmedabad’s new Danapith Fire Station in the Khadia ward is ready for operation after delays caused by heritage regulations and traffic restrictions, with the facility expected to open within 15 days.

The Ahmedabad Municipal Corporation (AMC) has completed the reconstruction of the nearly 80-year-old fire station and its 40-year-old staff quarters at a cost of ₹52.92 crore. The project has received its Fire No Objection Certificate (NOC), while the application for Building Use (BU) permission is under process.

The facility, which also includes staff accommodation and a multi-level parking complex, is expected to become operational once the remaining approvals are secured.

Fire Station Equipped With Modern Facilities

Developed on a 5,253.40-square-metre plot, the project has a total built-up area of 19,827.31 square metres.

The new fire station has a ground floor and five upper floors. It houses the Chief Fire Officer’s office, reception, junior staff office, control room, multipurpose hall, equipment museum, separate cabins for senior and junior officers, and a gymnasium.

A garage with space for five large fire vehicles has also been constructed. While the lift installation has been completed, some finishing work, including pipe fitting, is still underway.

Parking for 525 Vehicles, 31 Staff Quarters

The project also includes a multi-level parking facility with a basement, ground floor and four additional levels. It can accommodate 303 four-wheelers and 222 two-wheelers.

A separate residential and administrative building, comprising a ground floor and five upper floors, houses 31 residential units for fire department personnel.

These include 25 one-bedroom-hall-kitchen (1-BHK) units, four 2-BHK units and two 3-BHK units.

Heritage Rules, Traffic Restrictions Delayed Project

The AMC awarded the project to Satyam Construction Company through a ₹52.92-crore tender in September 2022. The original deadline for completion was September 2024.

However, construction faced several obstacles. Electricity lines passing through the plot had to be relocated, while removing the foundations of the old structures and clearing trees added to the timeline.

The movement of people and goods around the nearby Manek Chowk vegetable market, along with traffic restrictions in the walled city, also affected construction work.

The project's location within Ahmedabad's UNESCO World Heritage City zone brought additional requirements. A Heritage Impact Assessment (HIA) report was prepared by CEPT, following which the design underwent changes based on recommendations from the Heritage Conservation Committee (HCC) and UNESCO.

Changes were made to the building's facade, colour scheme and CNC-cut jali designs to comply with heritage guidelines.

UNESCO Raised Objections Over Building Height

An AMC official said UNESCO had raised objections to the building's height after the structure had already undergone changes, prompting discussions on modifying the existing design.

A revised design was subsequently prepared, and UNESCO finalised one of the proposed designs. The building's facade was constructed accordingly.

The official said traffic-related difficulties and other site constraints also contributed to the delay. The construction is now complete, and the AMC has submitted its application for BU permission.

The fire station is expected to become operational within the next 15 days, subject to the completion of the approval process.